NOV/DEC 2006:

Cover Story:
Military Construction

Features: 
What We Build:

Hard Hat Heroes 
Issues & Trends:
Feds and Jobsite Security

Departments:
Editor's Notebook
Guest Commentary
Construction Disputes
Internet Job Apps
— Info Tech:
     Lightning Switch
     EPIC Inc.
     VaporLab
The Punchlist

Inside AGC:
President's Message
CEO's Message
Chapter Corner
Midyear Recap
Services & Products
AGCxml Debuts

 

View all archives >>
<< Home

 

Departments — November/December 2006

Betting the Farm: Three Rules for Construction Disputes

Contractors need to avoid taking irrevocable positions and be willing to explore and accept reasonable compromises

Stuart Sobel
ATTORNEY AT LAW

Stuart Sobel is a shareholder of the Coral Gables-based firm Siegfried, Rivera, Lerner, De La Torre & Sobel P.A. He specializes in trial, arbitration and appeal of business and tort disputes with an emphasis on construction-related litigation.
Web site: www.siegfriedrivera.com

H. Hugh McConnell
ATTORNEY AT LAW

H. Hugh McConnell is with the Coral Gables-based law firm of Siegfried, Rivera, Lerner, De La Torre & Sobel P.A. He specializes in construction litigation and appellate practice. McConnell received his law degree from Northeastern University.

In a recent ruling by the U.S. District Court for the Eastern District of Philadelphia, a metal panel subcontractor learned a hard lesson about walking off a job in a dispute with the contractor. The case was LBL Skysystems (USA) Corp. v. APG-America Inc. and also involved the firms' respective sureties.

The Facts of the Case

LBL had hired APG to install metal panels in the new USAirways International Terminal at the Philadelphia airport. After two years of working on the project, APG attempted to reduce its scope by claiming it had erroneously supplied the support steel for attaching its panels to the building. APG delivered an ultimatum to LBL: Pay approximately $5 million for the design, engineering, fabrication and installation of the support steel already in place or APG would leave the job.

LBL investigated and confirmed that the support steel was part of APG's contract. APG had hired an independent structural engineer to design the steel that it now said deserved a change order. APG's bid documents, design drawings, purchasing and pay applications all confirmed that APG had indeed included the support steel in the original contract up until that point.

LBL tried to dissuade APG from taking the drastic step of walking off the job. But APG followed through on its threat and reduced its manpower nearly to zero, a level where work could not progress at the rate needed to keep LBL from defaulting on its own contract with USAirways.

At this critical stage, LBL could afford neither to lose its key subcontractor nor pay an extra $5 million for work it had already purchased under the existing subcontract. LBL called upon APG's performance bond surety to find a solution, but the surety delayed a decision and ultimately declined to complete APG's work or fund LBL's completion of it.

LBL was left with no choice but to do the work itself at its own cost, which it did. Although it was an experienced curtain-wall fabricator, LBL was not in the metal-panel business and could not complete the work as efficiently as APG. Not surprisingly, it cost LBL a lot more to complete APG's scope of work than it would have cost APG itself. LBL deducted those costs from the balance remaining in the subcontract and sued APG for the difference.

After a hard-fought trial, the U.S. District Court agreed with LBL, finding that the support steel was part of APG's scope of work in the subcontract. The court awarded LBL a judgment against both APG and its surety for nearly $2 million, including interest. In addition, LBL is now seeking to recover its fees from APG and its surety, which could more than double APG's loss.

The disastrous miscalculations and missteps by APG now threaten to close the doors on this third-generation business. Why did this happen? How could it have been avoided?

Subcontract Provisions

Putting aside APG's position on the disputed work, perhaps its fatal step was following through on its threat without considering the full implications of its subcontract. As is common, the prime contract between USAirways and LBL was also incorporated into the LBL/APG subcontract. During negotiation of the subcontract, a provision was stricken that would have authorized APG to stop work during a dispute. That left APG bound to a provision in the prime contract that expressly required it to continue "working expeditiously" during a dispute.

The court awarded LOL a judgment against both APG and its surety for nearly $2 million, including interest.

The court decided that APG's abandonment was inexcusable whether or not APG's position on the scope dispute had merit. It ruled that there was a material breach of the contract, entitling LBL to recover the costs of completing APG's work even if the cost to LBL exceeded what it might have cost APG to continue working.

Lessons Learned

Three lessons come to mind from the Philadelphia airport debacle:

  • Read and understand the entire contract.
  • Avoid taking irrevocable positions that may excuse performance by your adversary.
  • Be willing to explore and accept a reasonable compromise.

Construction agreements usually include by reference documents that are separate from the single contract signed by the parties. Subcontracts incorporate the terms of prime contracts, and general and special conditions.

Also, bonds and insurance policies required by the contract language impact the rights and obligations of the parties. The total package of documents that make up the subcontract must be carefully studied as an integrated agreement. The time to understand the agreement is not after a dispute has materialized but before it is signed, before work begins and before disputes arise.

Perhaps APG's fatal step was acting on its threat without considering the full implications of its subcontract.

In this case, APG should not have walked off the job, no matter how valid its position about the scope of work might have been. The subcontract anticipated that disputes might arise and prohibited APG from stopping its work, whatever the dispute. APG also took an irrevocable position and ignored all reasonable efforts at compromise, which left LBL with no alternative except to terminate APG and sue both it and its surety.
What should have been a negotiable dispute over half a million dollars became a liability for millions.

 

 
Constructor is a publication of McGraw-Hill Construction [ © 2008, all rights reserved ]
Terms of Use | Privacy Policy | Contact Us | Subscribe